Integrated electrical design for a data center to Tier III, reviewed with a Uptime Institute consultant until the study was approved.
Power Engineering Consortium prepared the integrated electrical study for a data center to Tier III requirements, so critical loads keep a second feed path and systems can be maintained without taking the service down.
The scope covered main and sub-distribution boards, cable routing, HVAC power, fire-system interlocking, and grounding and lightning protection to ANSI/TIA-942. The study was reviewed with a Uptime Institute accredited consultant until the comments were closed and the design was approved, including Tier III design certification.