Engineering Audit

Engineering and financial audit of an 80 MW solar plant

Adra, Rural Damascus

Aerial view of the 80 MW solar plant area in Adra

Engineering and financial audit of an 80 MW photovoltaic plant in Adra, connected to the 230 kV transmission network.

Power Engineering Consortium audited one of the largest renewable projects in Syria: an 80 MW photovoltaic plant on about 930 dunums in Adra, built to sell its output to the transmission utility at 230 kV.

The review covered 147,840 bifacial modules, TMEIC central inverters, outdoor combiner boxes at 1,500 V DC, and a GIS substation stepping up from 20 kV to 230 kV, together with losses, protection, grid-code compliance, capital and operating cost, and the power-purchase model.

All projects
Solar arrays at the Ashrafieh Sahnaia plant
Renewable Energy

630 kW solar plant in Ashrafieh Sahnaia

Aerial view of the pharmaceutical plant solar installation in Zabadin
Renewable Energy

Off-grid solar plant for a pharmaceutical factory

Server room illustrating a Tier III data center
Critical Facilities

Tier III electrical design for a data center